Supplier Calendar Calculation

  • Supplier Calendar – Clipper -Supplier Test
  • Step 1 : Define Exceptions

    Navigation: Setup and maintenance 🡪  Global Search 🡪 Manage Schedule Exceptions 🡪 Create 🡪 Enter the Required Details and Exception Days 🡪 Save and Close.

  • Step 2 : Define Calendars

    Navigation: Setup and maintenance 🡪  Search 🡪 Manage Schedule 🡪 Create. Add Workday patterns and Schedule Exception to the calendar 🡪 Save and Close.

  • Step 4 :Attach the Supplier Calendar to supplier in Manage Supply Network model.
  • Step 5 : Run RP Plan.
  • Case 1 – Suggested Due Date Considering Workday pattern. (4 Days on)

    Suggested Order Date – 11/04/2025 (Friday Holiday)

    Preprocessing Lead Time – 0 Days

    Suggested Start Date – 14/04/2025 (Monday)

    Processing Lead Time – 11 Days

    Suggested Ship Date – 01/05/2025 (Thursday)

    Post Processing Lead time – 2 Days

    Suggested Due Date – 05/05/2025

     

    Case 2 –  Suggested Due Date Considering Exceptions.

  • Suggested Order Date – 25/11/2025 (Tuesday)

    Preprocessing Lead Time – 0 Days

    Suggested Start Date – 25/11/2025 (Tuesday)

    Processing Lead Time – 11 Days

    Exception Days – 12th Dec to 31st Dec.

    Suggested Ship Date – 01/01/2026 (Thursday)

    Post Processing Lead time – 2 Days

    Suggested Due Date – 05/01/2026