MPS/MRP planning attributes

Navigation path: Inventory>Items>Master Items>General Planning (T)

Refer to the table below for the setup of each attribute.

 

Attribute Valid

values

Purpose Comment Setup
Planning Not Select the option Not Planned: The item does not  
Method Planned, that Planning require long–term planning of
  MRP uses to decide material requirements. Choose this
  planning, when to plan the option for high volume and/or low
  MPS item cost items that do not warrant the
  planning,   administrative overhead of
  MRP/DRP   planning; typically dependent
  Planned,   demand items. You cannot use this
  MPS/DRP   option unless the Pick Components
  Planned,   attribute is checked.
  DRP   MRP planning: Choose this option
  Planned   for non–critical items that do not
      require manual planning control,
      typically dependent demand items.
      MPS planning: You master
      schedule the item and require
      manual planning control. Choose
      this option for items with
      independent demand, items that are
      critical to your business, or items
      that control critical resources.
      MRP/DRP Planned: Choose this
      option when you want both MRP
      and DRP planning for the item.
      MPS/DRP Planned: Choose this
      option when you want both MRP
      and DRP planning for the item.
      DRP Planned: Choose this option
      when you have multiple
      organizations for which you do
      Distribution Requirements
      Planning for the item.
Forecast Consume, Select an option This is appropriate only for items  
Control Consume to determine the that are models, option classes,
  and derive, types of demand options, or mandatory components
  None you place for the of models and option classes.
    item. This guides Consume: forecast demand
    the key processes directly, rather than by exploding
    of two–level forecast demand.
    master Consume and derive: forecast
    scheduling: demand directly, explode forecast
    forecast demand, or use a combination of
    explosion, both methods.
    forecast None: place sales order demand
    consumption, but do not forecast demand.
    planning,  
    production relief,  
    and shipment  
    relief.  

 

Attribute Valid

values

Purpose Comment Setup
Exception Set   Enter the name The item–level planning  
  of the planning exceptions include:
  exception set that overcommitted, shortage, excess,
  groups together and repetitive variance. The
  the sensitivity planning process uses this attribute
  controls and to decide when to raise planning
  exception time exceptions for the item.
  periods for item–  
  level planning  
  exceptions for  
  the item.  
Create   Indicates if    
Supply supply can be
  suggested for this
  item.
Critical   If selected, flags This allows you to plan master  
Component the item as a scheduled items with respect to
  critical only critical component and their
  component for material resource constraints.
  MPS and DRP  
  planning.  
Pegging Soft Enter the pegging Soft Pegging: allocates supply to  
  Pegging, option. demand based on the Reservation
  End   Level option set in the Plan
  Assembly   options.
  Pegging,   End Assembly Pegging: traces the
  End   end assembly the item is pegged to
  Assembly/   at the top of the bill of material.
  Soft   Even if you do not select end
  Pegging,   assembly pegging, you can still
  Hard   calculate and view end assemblies
  Pegging,   on–line.
  End   End Assembly/ Soft Pegging:
  Assembly/   Choose this option for both soft
  Hard   pegging and end assembly
  Pegging,   pegging.
  None   Hard Pegging: allocates supply to
      demand based on the Reservation
      Level option set in the Plan
      options. This pegs supply to
      demand and demand to supply by
      project at all levels of a bill of
      material. This allows you to pre–
      allocate supply to demand and
      generate planned orders based on
      the plan level options.
      End Assembly/ Hard Pegging:
      Choose this option for both hard
      pegging and end assembly
      pegging.
      None: disables project material
      allocation, end assembly pegging,
      and full pegging.
Planned   Indicates if the This means that material can be  
Inventory item is an stored at the item level without
Point Inventory Point losing materials or quality
  item. characteristics. Inventory Points
    generally point to major stocking
    phases in the manufacturing cycle.

 

Attribute Valid

values

Purpose Comment Setup
Shrinkage   Enter a factor The planning process inflates  
Rate that represents demand to compensate for this
  the average expected loss.
  amount of  
  material expected  
  to lose during  
  manufacturing or  
  in storage.  
Round Order Quantities 1   Indicate whether the planning process uses decimal or whole number values when calculating planned order

quantities or repetitive rates.

When this option is checked, decimal values round up (never down) to the next whole number. The planning process carries any excess quantities and rates forward into subsequent periods as additional supply.  
Acceptable Early Days 2   Enter the number of days before which the planning process will not reschedule orders. The planning process only suggests rescheduling out if the new calculated order date is later than the original order due date plus the acceptable early days; the new calculated order does not violate the order of current scheduled receipts.

This applies to discrete items only.

 
Calculate   Indicate whether On the Planning Detail Report,  
ATP 3 to calculate and ATP is calculated as
  print available to ATP = Planned production –
  promise (ATP) committed demand
  on the Planning  
  Detail Report.  
Reduce MPS None, Past Decide when to None: Do not reduce order  
4 Due, reduce master quantities on the MPS.
  Demand production Past Due: Reduce order quantities
  Time Fence, schedule (MPS) on MPS entries to zero when the
  Planning quantities to entry is past due.
  time Fence zero. Demand Time Fence: Reduce
      order quantities on MPS entries to
      zero when the due date moves
      inside the demand time fence.
      Planning time Fence: Reduce
      order quantities on MPS entries to
      zero when the due date moves
      inside the planning time fence.

 

Attribute Valid

values

Purpose Comment Setup
Planning Cumulative Determine a Planning calculates the planning  
Time Fence mfg. lead point in time time fence as the plan date (or the
Days 5 time, inside which next workday if the plan is
  Cumulative certain generated on a non workday) plus
  total lead restrictions on the value entered here.
  time, Total planning Cumulative mfg. lead time: The
  lead time, recommendations cumulative manufacturing lead
  User– apply. time for the item.
  defined   Cumulative total lead time: The
      total manufacturing lead time for
      the item.
      Total lead time: The total lead time
      for the item.
      User–defined: The value you enter
      for Planning Time Fence
      Days.
Demand Cumulative Determine a Used to reduce the risk of carrying  
Time Fence mfg. lead point in time excess inventory.
Days time, inside which the Planning also uses the demand
  Cumulative planning process time fence when loading master
  total lead ignores forecast schedules. The demand time fence
  time, Total demand and is calculated as the start date of the
  lead time, considers only master schedule load plus the value
  User– sales order entered.
  defined demand when Calculate the demand time fence as
    calculating gross the plan date (or the next workday
    requirements. if the plan is generated on a non
      workday) plus:
      Cumulative mfg. lead time: The
      cumulative manufacturing lead
      time for the item.
      Cumulative total lead time: The
      total manufacturing lead time for
      the item.
      Total lead time: The total lead time
      for the item.
      User–defined: The value you enter
      for Planning Time Fence
      Days.

 

Attribute Valid

values

Purpose Comment Setup
Release Time Cumulative Determine a No material availability check is  
Fence Days 6 mfg. lead point in time performed before WIP jobs are
  time, inside which released.
  Cumulative planned orders Calculate the release time fence as
  total lead for discretely the plan date (or the next workday
  time, Total planned items are if the plan is generated on a non
  lead time, automatically workday) plus the value entered
  User– released as WIP here.
  defined, Do jobs or purchase Cumulative mfg. lead time: The
  not auto– requisitions. cumulative manufacturing lead
  release, Do   time for the item.
  not release   Cumulative total lead time: The
  (Kanban)   total manufacturing lead time for
      the item.
      Total lead time: The total lead time
      for the item.
      User–defined: The value you enter
      for Planning Time Fence
      Days.
      Do not auto–release: The item
      cannot be auto–released.
      Do not release (Kanban): For
      Kanban items prevent release of
      planned orders manually or
      automatically.
Substitution Cumulative Calculates until what time a substitute can be considered for an item. Cumulative mfg. lead time: The  
Window mfg. lead time

Cumulative

cumulative manufacturing lead time

for the item.

  total lead Cumulative total lead time: The total
  time manufacturing lead time for the item.
  Total lead Total lead time: The total lead time for
  time the item.
  User-defined User-defined: The value you enter.
Recent Posts

Start typing and press Enter to search