Everyday(four times a day) project, budget and forecast files are interfaced from Tririga to oracle through integration DLK , OIC and finally in cloud. However some of the project budget were not updated in oracle.

Solution:

 

Navigation:

Home>>>Projects>>>Project Financial Management>>>Search project>>>Manage Project Budget>>>Select current working Version>>>Add>>>Financial Resource.